- Location: 1250 Springbrook Road, Walnut Creek, California
- Primary Firm: Calpo Hom & Dong Architects, Inc.
- Owner: Central Contra Costa Sanitary District
- Owner's Designee: Edgar Lopez, Project Manager
- Design Service Time: 12 Months
- Construction Status: Completed
- Construction Completed: March 2012
- Construction Time: 24 Months
- Cost Estimate: $12,000,000
- Bid Award: $8,455,000
- No. of Change Orders: Not disclosed
- Prime Contractor: Bobo Construction Elk Grove, CA
- Contractor Project Manager: Chris Baker / 916-685-2285
CCCSD Collection System Operations Crew Facility
CCCSD Collection System Operations Crew Facility
Contact | Ann Farrell, General Manager CCCSD, 925-228-9500
Address | 5019 Imhoff Place, Martinez, CA
New Two-Story Replacement Facility (+/-24,249 sf) for the Central Contra Costa Sanitary District Collection Systems Operations Division and master planning of the existing Corporation Yard. The facilities include Crew Rooms, Lockers, Showers, Administration Offices, Fitness Center, and High-Bay Warehouse. Site work includes Covered Loading / Unloading Areas, Material Bins, Laydown Yard, Fleet Parking, and storm water retention on a 3.5 acre site that varies 70' in elevation across the site.