- Project: Lincoln Fire Station No. 33
- Location: 17 McBean Park Drive, Lincoln, CA
- Primary Firm: Calpo Hom & Dong Architects, Inc.
- Owner: City of Lincoln
- Owner's Designee: Mike Davis, Fire Chief
- Design Service Time: 6 Months
- Construction Status: Construction completed January 2008
- Construction Time: 12 Months, Completed On-Schedule
- Cost Estimate: $3,960,000.00
- Bid Award: $3,211,705.00 ($256/sf)
- No. of Change Orders: Not Disclosed
- Cost of Change Orders: $658,990.00 (20.5%)
- Site Remediation: $233,128.00 (7.3%)
- Unforeseen: $110,036.00 (3.4%)
- Owner: $286,606.00 (8.9%)
- Design: $286,606.00 (8.9%)
- Prime Contractor: ZCON Builders, Roseville
- Contractor Project Manager: Larry Leedy / 916-786-8003
Lincoln Fire Station No. 33
Lincoln Fire Station No. 33
Contact | Michael Davis, Fire Chief, 916-645-4040
Address | 126 Joiner Parkway, Lincoln, CA 95648
Lincoln Fire Station No. 33 is a two-story new, +/-12,000 square foot facility. The building design ties in with the character of the surrounding community. This Fire Station includes an Apparatus Bay (2x2 vehicles deep, plus one), Living Quarters for Ten Person Crew accommodations, Battalion Chief’s Quarters, Exercise Room, Equipment Turnout Room and Storage Mezzanine.