- Project: West Sacramento Fire Station No. 45
- Location: 2040 Lake Washington Blvd., Sacramento, CA
- Primary Firm: Calpo Hom & Dong Architects, Inc.
- Owner: City of West Sacramento
- Owner's Designee: Randy Goodwin, City Building Official
- Design Service Time: 8 Months
- Construction Status: Construction completed May 2007
- Construction Time: 12 Months
- Cost Estimate: $8,100,000.00
- Bid Award: $6,928,798.00
- No. of Change Orders: Not Disclosed
- Cost of Change Orders: $674,908.00 (9.7%)
- Prime Contractor: Allen L. Bender, Inc., West Sacramento
- Contractor Project Manager: Joel Gallion / 916-372-2190
West Sacramento Fire Station No. 45
West Sacramento Fire Station No. 45
Contact | Gary Fredericksen, Division Chief, 916-617-4600
Address | 2040 Lake Washington Blvd., West Sacramento, CA 95605
Planning and design of new Two-Story Fire Station (±27,000 square feet). Facility includes Apparatus Bays (4 x 2 vehicles deep), Administrative Offices, Living Quarters with 12-Person Crew accommodations, Captain’s and Duty Chief’s Quarters, Community/Training Room, Exercise Room, Equipment Turnout Areas, Decontamination Areas, and City Police Service Center. Masonry and Wood Frame construction.